1.
In which process group do we transfer resources to other systems?
a. Initiating
b. Executing
c. Controlling
d. Planning
e. Closing
2.
The change control system must include all but which of the following?
a. The paperwork
b. The tracking system
c. Verbal approvals
d. Authorization approval levels
3.
In order to ensure that the receiver has understood the message the sender must:
a. hand deliver the message
b. receive a signature of acceptance
c. receive feedback
d. b and c
4.
Decomposition occurs during:
a. scope planning
b. scope verification
c. scope definition
d. project initiation
5.
Which of the following CANNOT be tracked using the WBS?
a. Time
b. Cost
c. Quality
d. Amount of work